#240 - Schneider Parameters to configure in the TeSys Island

- Connect to the island using SoMove

- Configure the communication card

- For the first DOL enable the Load Energy Monitoring and also assign the SIL Group

- For a Double-Direction motor configure accordingly, it will automatically assign two DOL to the avatar

- Parameters to update:

> Power Supply: 3 Phase

> Upstream Voltage: 380 V

> Rating: kW

> Product reference

- Settings:

> Enable all Electrical protection. Phase reversal may have to be updated depending on the motor direction.

> For Load Protection, enable Jam, Stall, Undercurrent and Overcurrent.