#72 - Rockwell PLC change version of project

In this post a project version upgrade in a Rockwell PLC is described. This could be useful to keep the project in sync with the latest corrections done by the manufacturer, such as improvements related to cyber-security.
Open the original project:

Click on Change Controller... and select the desired version to upgrade:

The project is then updated to the desired version. 

The controller CPU must then be upgraded to the correct Firmware version accordingly. 